Renewables Installation - Labour Supply – Procedure Development

Challenge 

The challenge was to complete reviews of the current client installation manuals and generate detailed workpack documents for the Wind Energy Converter AREVA M500. 

Solution 

  • Prerequisites document 
  • Gap analysis of existing installation manuals 
  • HAZOP study 
  • Generate Offshore Workpacks in a format that has been proven in the field both on and offshore incorporated with the installation procedures 
  • PPE Requirements document 

Results 

  • Gap analysis of existing installation manuals highlighting key areas 
  • Completed documentation approved by client 
  • Successful onshore trial use of the workpacks 

Maximising our value 

  • Key areas for review highlighted to customer based on 3sun Group construction knowledge 
  • Successful use of the Workpacks during onshore trials and offshore construction