Oil & Gas Inspection - Offshore Rope Access and Rigging Services

Challenge 

Cost effective installation of lateral tension rings on the conductor at the spider deck level of platform. 

Solution 

  • Remove the tension ring 
  • Provide expert rope access riggers to “cross Haul� the 1.5 ton tension ring system 
  • Remove four hydraulic cylinders 
  • Remove four 30ton sling sets from around main structure 
  • Project management, planning and execution 
  • Maintaining safe methods of work 
  • Provide full equipment certification, management and tracking system 

Result 

  • Tension ring system removed 
  • Maintaining safe systems of work during rope access operations 
  • No reportable lost-time incidents 

Maximising our value 

  • Maintaining client’s safety culture 
  • Reduction in offshore remedial works due to closing-out all defects whilst on-site 
  • Provide technical advice and assistance 
  • Completing work scopes within designated timescales thus reducing costs of return visits